Chervonoarmiyska – One of the Longest Underground lines in the World

0

underground station in Kiev

Kiev (Ukraine) is in the middle of the top 10 European capitals having the greatest subversive lines. The Vystavochniy center is a new station of the Kurenivsko-Chervonoarmiyska line in Kiev metro which is still under construction.

underground station in Kiev

According to the State building Program, the station had to be ready by 2008. The time was up. However, its vigorous reconstruction started in 2010 with resolution of 2 building grounds used for meeting of channel shields. The Vystavochniy centre station connects 2 lines. Acting stations are marked with blue, reconstructed areas with over shield chambers are marked with red. The yellow color is used to denote the areas that will be launched by the end of 2011. White parts define standpoint stations.

underground station in Kiev

The skull of the tunneling shield “Victoria” is seen in the shield chamber.

underground station in Kiev

The original part of its tail contains a transport line for mine tracking.

underground station in Kiev

The Tail.

underground station in Kiev

This region is processed with the assist of the non-mechanized protect.

underground station in Kiev

The loading machine delivers lining blocks.

underground station in Kiev

The tail of the non-mechanized shield.

station in Kiev

Trench of the Vystavochniy centre position.

station in Kiev

The initial shield was put into process 4 months ago. Only 7 months are left now till the intended launch of the station.

station in Kiev

It’s intended to launch the trailing button. In this case trains will come with the interval of 90 sec as complete freeing of the switch will be required first.

station in Kiev

60% of the first line is complete and just 2-3 months are needed to achieve the essential works. As soon as the tunnel is constructed concrete placement will be ongoing.

station in Kiev

The second tunneling shield “Victoria” can’t boast of substantial labor achievement as just a small part of the works has been done. Luckily, there are less lines and communications on its way that’s why there is a expect that the building will be over in time.

station in Kiev

The third and non-mechanized shield on the 2nd line demonstrates superior consequences having passed 100 meters out of the planned 300 meters.

station in Kiev

station in Kiev

underground station in Kiev

station in Kiev

station in Kiev

underground station in Kiev